- 1125 Russel St
20 Year Sky Lantern

- 1125 - 2 weeks

  • $0.00

email address:  tntsales2@gmail.com 

Hours

Monday - March 16th - 8 hours (9~5)
- Prepped rooms
- knockdown on ceiling done
- took doors off all rooms
- partial cabinets removed.
- removed all nails and screws

Tuesday - March 17th - 8 hours  (9~7)  1hr lunch
- Insulated all outside wall outlets,
- Cleaned some walls (TSP)
- Spray foamed Filled and 1st drywall coat on holes
- Touched up ceilings where scrapped.
- Removed bathroom vanities (Plumping is all glued which will make it difficult to install new as is, so will have to cut and glue back, possibly replumb new)
- Back door floor is wet and will need fixing.  10" x 5 feet
- Scrap stored in shed until removal time

Wednesday - March 18th - 8 hours  (9:30 ~ 3:30, 8~10pm)
- Fix master bath Floor
- Clean walls (TSP)
- Prep Windows, tape and mask

Thursday
- March 19th - 7 hours  (11 ~ 6pm)
- Clean walls (TSP)
- Drywall repairs

Friday - March 20th - 8 hours  (12 ~ 8pm)
- Took more trim off in bathroom and kitchen
- Removed carpet and padding
- Cleaned up and stored scrap in shed
- Prep n Filled some nail holes
- Brad nailed a few things, and taped other areas needed nailed (alot of loose trim)

Saturday - March 21st - 6 hours  (12 ~ 6pm)
- Remove main sink and counter
- Remove carpet tack strips in main room
- Pulled up staples / Prepped main room
- clean and put trash in shed

Monday - March 23rd - 8 hours  (9~12 ~ 2~8pm)
- Remove carpet tack strips
- 2 Trips to the landfill
- Pull up/hammer down staples / Prep All bedrooms 

Tuesday - March 24th - 8 hrs  (10~4, 6~8pm)
- took off seams and taped (2nd coat on, 2 more to add)
- Finished hallway
- Drywall seams in kitchen

- added backer plate for door trims

Wednesday - March 25th - 2 hours  (10~12)
- 3rd coat drywall mud

Thursday - off

Friday - March 27th - 5 hrs  (9:30~4:30)
- 4th coat on seams
- brad nailed some trim
- unloaded truck
- Plastic paint protection over plumbing
- all doors in shed till cabinets in

Saturday - March 28th -  hrs  (10:30~)
- Sand and prime joints mudded
- Fill nail holes on walls
- Finish brad nail loose trim
- Fill holes around windows 
- Finish cleaning walls (TSP)

Sunday - Hopefully Prime -  hours  ( ~   )










====================================
FYI - 
====================================

- Need GFI under sink (20amp)
- back door has NO shims or screws to hold it in place

-------------------------------

Front stairs

- need permission from office, and must ask if permit is necessary if going bigger, thinking 4x8 

Write a review

Note: HTML is not translated!
    Bad           Good
  • Product Code: 1125-1
  • Availability: Pre-Order
Best
Patch
Eco
100
Good Fuel Patches
Bad Fuel Patches
Sky Lantern Sales | 4370 Chicago Dr. | Grandville, MI 49418 | U.S.A. | (616)-667-1090